The Barcelona team will have to return to the Estadi Olimpix Lluis Companys at the start of the 2027/28 season.
Specifically, as reported by Spanish media, the renovation of Camp Nou is entering its final phase, and the final move will be due to the installation of a new roof.
The Espai Barca project timeline suggests that all three levels of the new stadium will be completed by April 2027.
This marks an important moment, but it also begins the most complex phase of construction: the installation of the massive roof.
This engineering effort is expected to take approximately four months.
Since the installation requires the stadium to be completely empty for safety and construction reasons, Barcelona will be forced to play outside the Spotify Camp Nou for several weeks at the start of the 2027/28 season.